| Location:
Smederevo, Serbia
Date Completed: 2005
Project Description:
As part of our customer’s overall strategy to
boost steel production. Globex Corporation and Globex
Group were involved in a project to increase the capacity
of 2 existing 125-ton hot metal cranes to a new 170-ton
capacity. This project involved reinforcing the main
bridge girder and furnishing 2 new 170-ton hot metal
trolleys for the existing cranes. In cooperation with
Siemens a new control system with frequency inverter
was installed. The old and new control systems were
integrated in a new control pulpit.
Project Phases:
• Detailed mechanical design for crane reconstruction
• Detailed electrical design for crane reconstruction
• Specification of equipment
• Manufacturing and delivery of Trolleys
• QA during manufacturing
• Start-Up
• Testing
• Operating & Maintenance Manuals
• Training
• Training of Operating Personnel
|